Revolutionising the 4D BIM Process to Support Scheduling Requirements in Modular Construction

Mayouf, Mohammad and Jones, Jamie and Elghaish, Faris and Emam, Hassan and Ekanayake, E.M.A.C. and Ashayeri, Ilnaz (2024) Revolutionising the 4D BIM Process to Support Scheduling Requirements in Modular Construction. Sustainability, 16 (2). p. 476. ISSN 2071-1050

[img]
Preview
Text
sustainability-16-00476.pdf - Published Version
Available under License Creative Commons Attribution.

Download (4MB)

Abstract

Given the heightened importance of revolutionising 4D BIM-based construction scheduling in modular construction, it has become vital to explore how 4D-BIM could be integrated with the lean concept. Therefore, this research aims to develop a lean-integrated process model to revolutionise the 4D BIM-based construction scheduling in modular construction projects. A case study approach was used to obtain the data. The data was obtained using semi-structured interviews with construction scheduling professionals, site observations, and extracts from the BIM model used within the selected case in the UK. Findings showed that conventional (component/object based) 4D BIM supersedes conventional scheduling methods in terms of foreseeing potential implications during design and construction. The findings also showed that lean-integrated 4D BIM in modular construction have different considerations when compared with component/object-based scheduling. A lean-integrated 4D BIM process model was developed from the analysis and it was validated using an interactive workshop with eight participants from two UK construction companies and two modular construction manufacturers. The developed process model identified a number of considerations for 4D BIM in modular projects including constructability, operations, health and safety risks and time. This study suggested the further potential of 4D BIM in scheduling for modular construction projects.

Item Type: Article
Identification Number: https://doi.org/10.3390/su16020476
Dates:
DateEvent
2 January 2024Accepted
5 January 2024Published Online
Uncontrolled Keywords: 4D BIM, lean, scheduling,modular
Subjects: CAH13 - architecture, building and planning > CAH13-01 - architecture, building and planning > CAH13-01-02 - building
Divisions: Faculty of Computing, Engineering and the Built Environment > School of Engineering and the Built Environment > Dept. of Built Environment
Depositing User: Ilnaz Ashayeri
Date Deposited: 15 Feb 2024 12:37
Last Modified: 15 Feb 2024 12:37
URI: https://www.open-access.bcu.ac.uk/id/eprint/15244

Actions (login required)

View Item View Item

Research

In this section...